Sulaiman Building Restoration 68.35 Pct Complete, Ahead Of Schedule - Nanta

12/11/2026 03:46 PM

KUALA LUMPUR, Nov 12 (Bernama) -- Restoration of the historic Sulaiman Building, which houses the Asian International Arbitration Centre (AIAC), is seven days ahead of schedule, with 68.35 per cent of works completed as preparations continue to host international arbitration proceedings.

Works Minister Datuk Seri Alexander Nanta Linggi said particular attention was being given to ensuring the building’s adjacent annex or Pavilion Building was ready to host international proceedings.

“Ceiling repairs and the installation of a new air-conditioning system have been completed, while fire prevention system testing and finishing works are ongoing,” he said in a Facebook post today following a site visit this morning.

Nanta said he had instructed the Public Works Department (JKR) and AIAC to expedite the remaining works without compromising safety and quality.

He said the building’s readiness was crucial to supporting Malaysia's role as a host of international proceedings and promoting regional conflict resolution.

Opened in 1933, the Sulaiman Building is among Kuala Lumpur's historic landmarks and was designated a National Heritage Site in 2018.

It has housed AIAC facilities since 2014, serving as a centre for alternative dispute resolution, including arbitration and mediation.

-- BERNAMA

 


BERNAMA provides up-to-date authentic and comprehensive news and information which are disseminated via BERNAMA Wires; www.bernama.com; BERNAMA TV on Astro 502, unifi TV 631 and MYTV 121 channels and BERNAMA Radio on FM93.9 (Klang Valley), FM107.5 (Johor Bahru), FM107.9 (Kota Kinabalu) and FM100.9 (Kuching) frequencies.

Follow us on social media :
Facebook : @bernamaofficial, @bernamatv, @bernamaradio
Twitter : @bernama.com, @BernamaTV, @bernamaradio
Instagram : @bernamaofficial, @bernamatvofficial, @bernamaradioofficial
TikTok : @bernamaofficial

© 2026 BERNAMA   • Disclaimer   • Privacy Policy   • Security Policy