COVID–19 NEWS   COVID: Malaysia records increase in new cases, fatalities - Dr Noor Hisham | New COVID-19 cases drop 5.2 pct last week - Health Dg  | Witness still COVID-19 positive, Ahmad Zahid's corruption trial postponed | Japan's daily COVID cases top 180,000, set fresh record amid 7th wave | Canada approves first coronavirus vaccine for 6-month to 5-year-olds | 
BUSINESS

FGV installs its biggest renewable energy biogas power plant in Pahang

28/10/2020 05:01 PM

KUALA LUMPUR, Oct 28  -- FGV Holdings Bhd's (FGV) recently installed a biogas power plant at its Triang palm oil mill in Bera, Pahang, the company’s biggest renewable energy biogas power plant to date.

In a statement today, it said the plant has an installed capacity of 2.4 megawatts (MW).

“FGV’s Triang biogas power plant is successfully commissioned and fully-operational after receiving the Feed-in-Tariff (FiT) Completion Date (FiTCD) from the Malaysia Sustainable Energy Development Authority (SEDA) on Oct 20, 2020,” it said.

Through SEDA, FGV secures a quota for 2.0 MW of export capacity to Tenaga Nasional Berhad’s national grid for distribution to 15,000 homes in Felda Triang, Felda Sebertak, Felda Purun, Felda Bukit Kepayang and Felda Tementi which are located within a 30-kilometre radius from the biogas power plant.

Group chief executive officer, Datuk Haris Fadzilah Hassan said FGV’s Triang biogas power plant acts as an alternative form of green energy provider for TNB, which reduces the risk of outage to ensure a better and steadier stream of electricity.

“In line with the government’s renewable energy agenda, the power plant offers an efficient form of renewable energy through biogas from its Palm Oil Mill Effluent (POME) which reduces the need to burn more coal or natural gas that could potentially harm the environment,” he said.

The power plant also produces enough biogas to generate power transmitted to the TNB electrical substation which is connected to the national grid. 

During peak transmission, FGV said the biogas power plant is able to produce up to 10 million kilowatt-hours (kWh) per year, which translates into a revenue of RM5 million per year for the Palm Oil Mill (POM).

Apart from the Triang biogas power plant, FGV currently owns four other existing FiT biogas plants to export electricity to the national grid located in Mersing with 1.6 MW capacity, as well as in Maokil, Segamat and Tenggaroh with 1.2 MW capacity respectively.

-- BERNAMA

 

 


Bernama is the trusted source of reliable real-time comprehensive and accurate news for both the public and media practitioners. Our news is published at www.bernama.com ; BERNAMA TV on: Astro Channel 502, unifi TV Channel 631, MYTV Channel 121 IFLIX; and Bernama Radio broadcasting locally on FM93.9 in Klang Valley, Johor (FM107.5), Kota Kinabalu (FM107.9) and Kuching (FM100.9).

Follow us on social media :
Facebook : @bernamaofficial, @bernamatv, @bernamaradio
Twitter : @bernama.com, @BernamaTV, @bernamaradio
Instagram : @bernamaofficial, @bernamatvofficial, @bernamaradioofficial
TikTok : @bernamaofficial

© 2022 BERNAMA   • Disclaimer   • Privacy Policy   • Security Policy